Beaverbrook Branch: May update

12/05/2014

We are now entering the home stretch in the construction phase.  The exterior cladding is taking shape and will be completed by mid-month.  All interior finishes are progressing well with the overall project continuing to be on schedule.  Highlights include:

  • Carpeting and floor tiling has now been installed throughout the building
  • Meeting room doors and trim are nearing completion
  • All millwork has been delivered with much of it having been installed
  • All painting is nearing completion
  • All plumbing has been completed and inspected
  • Remaining exterior grounds and site work will commence this week with final paving and landscaping being completed by the end of May

Attached are some photos taken on May 1st  showing the latest progress on the building.