Construction progress on Ādisōke

View of exterior of Adisoke

Jul 04, 2023

If you’ve passed by the Ādisōke project site recently, there’s a good chance you witnessed a beehive of activity as the building continues to grow into the sky! The site has been busy with several concrete pours, and significant progress has been made on the first three floors of the facility.

In April, the concrete work for the main level of the facility was completed, and work began on the second floor.

In May, progress continued on the second level of the facility, and work on the level three skydeck began. Work also commenced on the feature staircase that will connect the main level (atrium) to the second level of the facility.

Another notable event in May was our first guided tour around the project site. The Ādisōke Project Team participated in Jane’s Walk 2023, offering a tour to members of the public. The tour was a great success, and we look forward to offering more opportunities in the future for residents to check out the project site. Thank you to everyone who joined us!

June continued to show progress as Ᾱdisōke rises higher into the sky. The third floor concrete work will soon be complete, and the fourth floor will soon start to be visible as you pass by the site.

In the coming weeks, we will finish pouring the third level of the facility. By the end of summer / early fall, the remaining two floors will be poured, bringing us one step closer to opening day in 2026!

Sign up for construction updates at adisoke.ca.